The rules for earthquake-prone buildings are changing, and for engineers, builders and building owners the work will look different. The Building (Earthquake-prone Buildings) Amendment Act 2026 received assent on 25 September, and most of it takes effect on 1 July 2027.
The Government says the changes will save building owners and the economy billions. “Today we are delivering significant reform that will save Kiwi building owners and the New Zealand economy a staggering $8.2 billion,” Building and Construction Minister Simon Watts said when the Act passed its third reading.
Only “buildings within scope” can now be classed as earthquake-prone. They’re buildings in medium or high seismic zones that are either unreinforced masonry, or tall buildings made of heavy materials and designed before 1976.
Mainly residential buildings, farm buildings, wharves, bridges and tanks are excluded. The Government expects around half of current earthquake-prone buildings to come off the register.
The seismic zone map, which has applied since 26 September, also changes the picture. Auckland, the Chatham Islands and the low-risk zone in the upper North Island leave the system entirely, while parts of coastal Otago and Stewart Island move up to the medium zone.
Instead of a general strengthening requirement, councils will now require one of two types of work. Urban unreinforced masonry buildings of one or two storeys will need “facade risk mitigation”.
Unreinforced masonry buildings of three or more storeys in an urban centre will need a “targeted retrofit”, and those outside an urban centre will need facade work. Tall heavy buildings need a targeted retrofit wherever they are, while one- or two-storey masonry buildings outside urban centres have no required measure.
Deadlines run from when a building first received its earthquake-prone notice. In medium seismic zones, owners have 12.5 years for priority buildings and 25 years for others. In high zones, it’s 7.5 and 15 years.
The shift from full strengthening to targeted work changes the type of job on offer. For many low-rise masonry buildings, the required work will be facade risk mitigation rather than a full strengthening project.
Heritage advocates have mixed views. Historic Places Wellington supported the facade-only rule for one- and two-storey masonry buildings and asked for it to be extended to three-storey buildings with secured facades.
Others warned the rules would cost some regions. In Dunedin, which is moving to a higher seismic zone in parts, heritage advocates told the select committee that changes could lead to demolitions, RNZ reported in March.
MBIE guidance on the new requirements was due to go out for consultation later this year. Engineers and builders who work on seismic projects should watch for it, because the guidance will set out what facade risk mitigation and targeted retrofits involve in practice.
Owners partway through strengthening work under the current rules face a decision. Before 1 July 2027, it’s worth checking with an engineer and the council whether the building will still be in scope, and what the new rules would require, before committing to the next stage of work.